Double Timber Door Restoration
Project Scope, refurbishment of external entrance door area.
Project process, remove and refurbish doors tracks and pelmet, remove window security grills, paint eaves and guttering.
Installed over fifty two years ago, these timber and glass doors had seen better days, Whilst in good condition, some damage prevented the opportunity to clear finish the doors, requiring timber repair, then application of water based gloss white.
Through the strip back stage, and two pack timber filler applied, awaiting fresh silicone before painting is commenced.
Once reassembled, overhead track cleaned and lubricated, doors painted and cleaned, windows cleaned, eves and guttering freshly painted.
Project time, three days.